Collection: container, compactor, bins - Solution from 225

poste_de_relevement

Issue
- surface treatment to the emission


Solution: surface treatment to the emission
-Hardware: spray hand, automatic spray with 5 L of NORASYSTEM C 520 L0
- Product : NORASYSTEM C 520 L0 (Link to product sheet).
- Determination : de 4 à 10%
- Cost : 0,05 € /m2

Back to top of page

2

Collection: trash / garbage collection truck - Solution from 3 322 € HT

zone_de_depotage

Issues

- Fresh Odors from fresh household waste decomposition

Solution : Treatment of gas on the top of the hopper / bin

- Hardware : AtomizerBox One (Link to product sheet).
- Product : NORASYSTEM C 520 L0 (Link to product sheet ).
- Determination : 2%
- Hourly : 0,71 € /H


2.1

Processing multi-flow receiving zone and fermentable - buckets - Solution from 9 136 € HT


Transfer/sort: dump, transfer docks / quai, Pré-Traitement Mécano organic.

degrilleur

Issue
-Reception pit, Multi-stream / multi flow area, juice, and bio-waste storage bins.

Solution: setting up a nozzle broadcasting system around the reception Sas / Airlock to process the atmosphere of the building and the vacuum at the opening of the doors.
- Hardware : AtomizerBox (Link to product sheet).
- Product : NORASYSTEM C 520 L0 (Link to product sheet).
-
Determination : 1 %
- Sequence : 30 sec action, 2 min interval
- Average hourly cost : = 0,71 €/H for 4 nozzles
- To work 16 hours / day = 351€/month

2.2

Washing Tower - Solution from 436 € HT

tour_de_lavage

The Physico-chemical absorption techniques consist to divert smelly compounds or COV from a gaseous state to an aqueous state via the assistance of Exchange columns. The Aqueous solutions used in the gas washing towers are most often associated with specifically targeted chemicals (sulphuric acid, bleach, soda...) to obtain a complete cleaning.

Issues
- Smelly odors from re-circulating water

Solution: Treatment of finishing in the last tower with mass reagent.
- Hardware : Dosing pump
- Product : NORASYSTEM C 503 L0 (Link to product sheet).
- Determination : 0,025%
- Cost = 11,2 €/m3 de-concentrate water (overflow)


3.1

Treatment / storage / valorization - Solution from 9 136 € HT

traitement_des_boues

At the level of macherfer / waste, the odors are light / fugitive when the slag are stored for less than 24 hours. However their smell reaches 865 or E/m3 when they are stored for several days. This increased smell is associated with an ammonia release (5 for fresh and 50 ppm for machefer / waste of several days).

Issues

- Ammonia

Solution: Setting up a nozzle broadcasting system around the reception Sas / Airlock to process the atmosphere of the building and the vacuum at the opening of the doors.

- Hardware : AtomizerBox (Link to product sheet).
- Product : NORASYSTEM C 503 L0 (Link to product sheet).
-
Determination : 1 %
- Sequence : 30 sec tretment, 2 min interval
- Average hourly cost : = 0,71 €/H for 4 nozzles
- To work 16 hours / day = 351€/month

3.2

Storage: Waste Ball - Solution from 9495 € HT

tour_de_lavage

Issues
- Odors from the decomposition of fresh household waste

Solution : Surface and remnant per-treatment
- Hardware : AtomizerBox (Link to product sheet). with proximity, compressor, detector flat nozzles jets from 9495 €
- Product : NORASYSTEM C 520 L0 (Link to product sheet).

- Amount of :
4 à 10%


 

3.3

Storage: CSDU and ISDND - Solution from 24 990 € HT

CSDU: (Ultimate Center of waste storage) and ISDND: (non-hazardous waste storage site)

tour_de_lavage

Issues
- household fresh Garbage odors

For the alveoli of more than 2500m 2
Solution: Dynamic spray arms of the gaseous skies
- Hardware : TurboFog Mach 1 à partir de 24 990 € HT (Link to product sheet).
- Product : NORASYSTEM C 503 L0 (Link to product sheet).

- Amount :
0,2%
- Function : Continue
- How it works : 16 hrs per day for 1 month
- Water consumption :
10,7 m3
- Energy consumption : 2200 KW.H
- reactive cost : 961 €